MTL-1 Montreal operational capacity

Company: WhiteFiber - Project: MTL-1

Subject kind
facility capacity
Statement date
2025-07-10
Promised amount
4.0 MW
Current status
stated

The claim, verbatim

Operating 4 MW gross AI data center in Montreal (MTL-1) with full capacity occupied by 14 customers under lease agreements averaging approximately 30 months

Source (primary)

WhiteFiber S-1 filed 2025-07-11 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We currently operate a 4 MW (gross) AI data center located in Montreal, Canada ("MTL-1"). MTL-1's full capacity is occupied by 14 customers under lease agreements with an average duration of approximately 30 months as of May 30, 2025.”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390025063338/ea0248382-s1_white.htm) in full (819,180 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms WhiteFiber S-1 filed 2025-07-11

Quote: “We currently operate a 4 MW (gross) AI data center located in Montreal, Canada ("MTL-1"). MTL-1's full capacity is occupied by 14 customers under lease agreements with an average duration of approximately 30 months as of May 30, 2025.”

View cached copy (2026-08-31)Live source ↗