Blönduós Campus GPU capacity contract
Company: WhiteFiber - Project: Blonduos Campus
The claim, verbatim
Executed contracts for 5.5 MW IT load at Blönduós Campus in Iceland with 6 MW total gross capacity
Source (primary)
WhiteFiber 10-K filed 2026-03-26 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We have executed contracts for 5.5 MW IT load at the data center...The facility has a 45 kW rack density and 6 MW (gross) total capacity.”
How we checked this
Checked on September 15, 2026. The cited source supports every part of this claim.
The filing says the company has executed contracts for 5.5 MW IT load at the Blönduós facility. It gives the facility's total capacity as 6 MW gross.
Confirmed in the source:
- WhiteFiber has executed contracts for 5.5 MW IT load at the Blönduós Campus data center in Iceland
- The facility has 6 MW (gross) total capacity
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/2042022/000121390026034341/ea0278305-10k_white.htm) in full (600,249 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber 10-K filed 2026-03-26
Quote: “We have executed contracts for 5.5 MW IT load at the data center...The facility has a 45 kW rack density and 6 MW (gross) total capacity.”