jain.com

Corsicana remaining power capacity for data center development

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2025-12-30
Promised amount
600.0 MW
Current status
stated

The claim, verbatim

The Company is taking strategic steps to develop approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes

Source (primary)

Riot 424B5 filed 2025-12-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “We are currently taking strategic steps to develop the approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes, with the objective of maximizing the value of our energy portfolio”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Riot 424B5 filed 2025-12-31

Quote: “We are currently taking strategic steps to develop the approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes, with the objective of maximizing the value of our energy portfolio”