Corsicana remaining power capacity for data center development
Company: Riot - Project: Corsicana
The claim, verbatim
The Company is taking strategic steps to develop approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes
Source (primary)
Riot 424B5 filed 2025-12-31 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We are currently taking strategic steps to develop the approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes, with the objective of maximizing the value of our energy portfolio”
How we checked this
Checked on September 16, 2026. The cited source supports every part of this claim.
The Data Center Development section states exactly this about the approximately 600 MW of remaining Corsicana capacity.
Confirmed in the source:
- The Company is taking strategic steps to develop approximately 600 MW of remaining power capacity at the Corsicana Facility
- That development is for large scale data center purposes
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1167419/000110465925125315/riot-20251230x424b5.htm) in full (151,163 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot 424B5 filed 2025-12-31
Quote: “We are currently taking strategic steps to develop the approximately 600 MW of remaining power capacity at the Corsicana Facility for large scale data center purposes, with the objective of maximizing the value of our energy portfolio”