Corsicana Facility Phase I Bitcoin build-out
Company: Riot - Project: Corsicana
The claim, verbatim
Completed Phase I of Bitcoin build-out at Corsicana Facility, equipped company with up to 400 additional MW of developed capacity for Bitcoin mining
Source (primary)
Riot DEF 14A filed 2026-04-30 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗
Quote: “We generated record revenue of $647.4 million, primarily driven by a significant improvement in the operating efficiency of our Bitcoin mining operations and completion of Phase I of the Bitcoin build-out at our Corsicana Facility, which equipped us with up to 400 additional megawatts ("MW") of developed capacity for Bitcoin mining.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Riot DEF 14A filed 2026-04-30
Quote: “We generated record revenue of $647.4 million, primarily driven by a significant improvement in the operating efficiency of our Bitcoin mining operations and completion of Phase I of the Bitcoin build-out at our Corsicana Facility, which equipped us with up to 400 additional megawatts ("MW") of developed capacity for Bitcoin mining.”