Promised amount
120.0 MW
Current status
stated

The claim, verbatim

Approximately 120+ MW energized across Denton and Marble sites as of presentation date

Source (primary)

Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “~120+ MW Energized Across Denton & Marble Sites”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The construction progress slide of the October 30, 2025 presentation states '~120+ MW Energized Across Denton & Marble Sites'.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11263/pdf/Core+Scientific+Investor+Update+Presentation+FINAL.pdf) in full (11,378 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Conference Call Presentation

Quote: “~120+ MW Energized Across Denton & Marble Sites”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-10-30.