Promised amount
20.0 MW
Current status
stated

The claim, verbatim

Austin, Texas site has approximately 20 MW of billable power

Source (primary)

Investor Conference Call Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Austin, Texas ~20MW Total Billable Power”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

Both the site map and the CoreWeave contracted-capacity table list Austin, Texas at about 20 MW.

Confirmed in the source:

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11263/pdf/Core+Scientific+Investor+Update+Presentation+FINAL.pdf) in full (11,378 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Investor Conference Call Presentation

Quote: “Austin, Texas ~20MW Total Billable Power”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2025-10-30.