ASDC 1 HPC delivery H2 2024
Company: Core Scientific - Project: Austin Data Center (ASDC)
What the later record shows
Outcome not yet confirmed
The only passage describes the Austin Campus at 3301 Hibbetts Road as a 16.5 MW data center. Nothing confirms an 80 MW ASDC 1 phase was delivered, delayed, or cancelled. The '37 MW billable' figure appears to describe a different campus.
“is a single building comprising two data halls that serve as a 16.5 MW data center located at 3301 Hibbetts Road in Austin, Texas”
2026-04-20 · core-scientific 8-K exhibit (d149019dex992.htm) View cached copy (2026-09-09)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
ASDC 1 phase with 80 MW to be delivered in H2 2024
Source (primary)
Second Quarter Fiscal Year 2024 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-09-01)Live source ↗
Quote: “H2 2024 ASDC 1 80MW Delivery”
How we checked this
Checked on October 17, 2026. The cited source supports part of this claim, but not all of it.
The deck shows a phased delivery timeline with an 80 MW phase starting in H2 2024. The flattened text of the chart does not clearly tie ASDC 1 to that 80 MW or to H2 2024.
Confirmed in the source:
- The presentation shows a 382 MW HPC data center (ASDC) delivery timeline running from H2 2024 through H1 2026, divided into phases ASDC 1 through ASDC 5
- The timeline includes an 80 MW delivery phase
We could not confirm this from the cited source:
- The extracted text of the timeline graphic does not clearly tie ASDC 1 to an 80 MW delivery
- The extracted text of the timeline graphic does not clearly place the ASDC 1 delivery in H2 2024
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_eb9c314ac28438fbd39d12d91c4e5bdc/corescientific/db/1066/11129/pdf/Core_Scientific_Q2_2024_Earnings_Presentation.pdf) in full (24,266 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “H2 2024 ASDC 1 80MW Delivery”
confirms Second Quarter Fiscal Year 2024 Earnings Presentation
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 H1 2025 H2 2025 H1 2026 ... 80MW Delivery”