Marathon Digital Holdings contracted capacity

Company: Applied Digital - Project: Ellendale

Subject kind
customer
Statement date
2022-10-11
Promised amount
276.0 MW
Current status
stated

The claim, verbatim

Marathon Digital Holdings exercised option for additional capacity, bringing total contracted capacity to 276MW, fully contracting out planned capacity at Ellendale

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Marathon Digital Holdings, Inc. exercised its option for additional capacity at Applied Blockchain's hosting facilities, bringing its total contracted capacity to 276MW and fully contracting out the planned capacity at the Ellendale facility”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release says Marathon exercised its option, bringing its total contracted capacity to 276MW and fully contracting Ellendale's planned capacity.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/42/applied-blockchain-reports-fiscal-first-quarter-2023/) in full (25,685 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised its option for additional capacity at Applied Blockchain's hosting facilities, bringing its total contracted capacity to 276MW and fully contracting out the planned capacity at the Ellendale facility”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised option for additional capacity at Applied Blockchain's hosting facilities, bringing its total contracted capacity to 276MW”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised option for additional capacity at Applied Blockchain’s hosting facilities, bringing its total contracted capacity to 276MW”

View cached copy (2026-09-29)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised option for additional capacity at Applied Blockchain’s hosting facilities, bringing its total contracted capacity to 276MW”

View cached copy (2026-10-03)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised option for additional capacity at Applied Blockchain’s hosting facilities, bringing its total contracted capacity to 276MW”

View cached copy (2026-10-06)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Marathon Digital Holdings, Inc. exercised option for additional capacity at Applied Blockchain's hosting facilities, bringing its total contracted capacity to 276MW”

View cached copy (2026-10-08)Live source ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2022-10-11.