Hyperscaler 400 MW capacity lease - letter of intent

Company: Applied Digital - Project: Ellendale

Subject kind
customer
Statement date
2024-10-21
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Applied Digital has executed a letter of intent with a US-based hyperscaler for a 400 MW capacity lease, including the 100 MW HPC Ellendale facility and additional facilities in Ellendale, North Dakota

Source (primary)

ARS (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “The Company has entered into exclusivity and executed a letter of intent with a US-based hyperscaler for a 400 MW capacity lease, inclusive of our current 100 MW facility and two forthcoming buildings in Ellendale, North Dakota”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K states the company executed a letter of intent with a US-based hyperscaler for a 400 MW lease covering its 100 MW facility and two forthcoming buildings in Ellendale.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001493152-24-042124/ars.pdf) in full (721,673 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms ARS

Quote: “The Company has entered into exclusivity and executed a letter of intent with a US-based hyperscaler for a 400 MW capacity lease, inclusive of our current 100 MW facility and two forthcoming buildings in Ellendale, North Dakota”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — stated
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-10-21.