Exclusivity extension with hyperscaler on July 26, 2024

Company: Applied Digital - Project: Ellendale

Subject kind
partnership
Statement date
2024-10-21
Event date
2024-07-26
Current status
stated

What the later record shows

Not a promise: a reported event · happened July 26, 2024

The claim reports an already-completed action: the exclusivity extension on July 26, 2024. The August 2024 release confirms the exclusivity LOI with a US-based hyperscaler.

“The Company has entered into exclusivity through an executed LOI with a US-based hyperscaler for 400 MW capacity”
2024-08-28 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital extended the initial exclusivity period under the letter of intent with a US-based hyperscaler for leasing the HPC Ellendale Facility

Source (primary)

ARS (IR page (ir.applieddigital.com), ir_release)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “On July 26, 2024, the Company extended the initial exclusivity period under the previously announced letter of intent with the U.S. based hyperscaler for leasing the HPC Ellendale Facility”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The 10-K says that on July 26, 2024 the company extended the initial exclusivity period under the hyperscaler letter of intent for leasing the HPC Ellendale Facility.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/sec-filings/all-sec-filings/content/0001493152-24-042124/ars.pdf) in full (721,673 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms ARS

Quote: “On July 26, 2024, the Company extended the initial exclusivity period under the previously announced letter of intent with the U.S. based hyperscaler for leasing the HPC Ellendale Facility”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2024-10-21.
October 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.