Ellendale facility restored to full operating capacity
Company: Applied Digital - Project: Ellendale
The claim, verbatim
Transformer repairs completed at Ellendale facility, site restored to full operating capacity as of June 28, 2024
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “As of June 28, 2024 the transformer-based repairs at the Company's Ellendale Data Center Hosting facility have been completed, and the site has been restored to full operating capacity.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Earnings Release
Quote: “As of June 28, 2024 the transformer-based repairs at the Company's Ellendale Data Center Hosting facility have been completed, and the site has been restored to full operating capacity.”