Ellendale facility energization timeline

Company: Applied Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2022-10-11
Promised by
2023-03-31
Current status
verified

What the later record shows

Delivered on time · happened March 4, 2023

Energization started on March 4, 2023, inside Q1 2023 as promised. Full energization was reported complete by July 24, 2023.

“The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“built a hosting facility, and began energizing the site on March 4, 2023.”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Energization of the Ellendale facility is expected in the first calendar quarter of 2023

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023”

How we checked this

Checked on October 10, 2026. The cited source supports every part of this claim.

The release states this expected timing directly.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/42/applied-blockchain-reports-fiscal-first-quarter-2023/) in full (25,685 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

confirms Earnings Release

Quote: “Energization of the Ellendale facility is expected in the first calendar quarter of 2023”

View cached copy (2026-09-25)Live source ↗Archive.org ↗

confirms Applied Digital 424B5 filed 2024-05-06

Quote: “built a hosting facility, and began energizing the site on March 4, 2023.”

View cached copy (2026-08-31)Live source ↗

confirms Earnings Release

Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

September 2, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 3, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-09-01 was the source's retrieval date; source published 2022-10-11.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.