Ellendale 180MW facility - second half capacity online
Company: Applied Digital - Project: Ellendale
What the later record shows
Delivered; the record does not say when
Later filings show the 180 MW Ellendale facility operating at full capacity, and FY ended May 31, 2024 is called its first full year of operations. No passage says when the second half was turned on, so whether June 2023 was met cannot be confirmed.
“built a hosting facility, and began energizing the site on March 4, 2023”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
“As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”
2024-10-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”
2025-07-29 · Applied Digital 10-K filed 2025-07-30 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The remainder of Ellendale facility's 180-Megawatt capacity will be turned on by the end of June
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “and the rest to be turned on by the end of June”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release says the company anticipated turning on the remainder of Ellendale's capacity by the end of June. This was a projection as of April 2023.
Confirmed in the source:
- In April 2023 Applied Digital said it anticipated the rest of the Ellendale facility's 180 MW capacity would be turned on by the end of June 2023
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,328 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “and the rest to be turned on by the end of June”
confirms Applied Digital 424B5 filed 2024-05-06
Quote: “built a hosting facility, and began energizing the site on March 4, 2023”
confirms Applied Digital 10-K filed 2025-07-30
Quote: “specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”
confirms Earnings Release
Quote: “As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”