Ellendale 180MW facility - first half capacity online
Company: Applied Digital - Project: Ellendale
What the later record shows
Delivered; the record does not say when
The full 180 MW was energized by July 24, 2023, so the first 90 MW was clearly turned on. No passage says whether that happened by the end of April 2023.
“The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”
2023-07-24 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The first half of Ellendale facility's 180-Megawatt capacity will be turned on by the end of April
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-01)Live source ↗Archive.org ↗
Quote: “The Company anticipates the first half of the facility's 180-Megawatt ("MW") capacity will be turned on by the end of April”
How we checked this
Checked on October 10, 2026. The cited source supports every part of this claim.
The release says the company anticipated turning on the first half of Ellendale's 180 MW by the end of April. This was a company projection made on April 6, 2023, not a report that it happened.
Confirmed in the source:
- In April 2023 Applied Digital said it anticipated the first half of the Ellendale facility's 180 MW capacity would be turned on by the end of April 2023
- The Ellendale facility has 180 MW of capacity
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,328 characters, retrieved September 1, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “The Company anticipates the first half of the facility's 180-Megawatt ("MW") capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “The Company anticipates the first half of the facility's 180-Megawatt ("MW") capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “The Company anticipates the first half of the facility's 180-Megawatt ("MW") capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “Energized second co-hosting facility in Ellendale, North Dakota in early March. The Company anticipates the first half of the facility's 180-Megawatt ("MW") capacity will be turned on by the end of April”
confirms Earnings Release
Quote: “The Company successfully completed the full energization of the facility after initiating the process in early March only six months after initial construction began.”