The claim, verbatim

On April 23, 2026, entered into two approximately 15-year leases with second U.S.-based investment-grade hyperscaler for aggregate 300 MW at Delta Forge 1

Source (primary)

Applied Digital 10-K filed 2026-07-29 (SEC EDGAR, sec_filing)
View cached copy (2026-08-30)Live source ↗

Quote: “On April 23, 2026, we entered into two approximately 15-year leases with a second U.S.-based investment-grade hyperscaler for an aggregate 300 MW of critical IT load at the campus.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital 10-K filed 2026-07-29

Quote: “On April 23, 2026, we entered into two approximately 15-year leases with a second U.S.-based investment-grade hyperscaler for an aggregate 300 MW of critical IT load at the campus.”