jain.com

Delta Forge 1 expected data center capacity

Company: Applied Digital - Project: Delta Forge 1

Subject kind
facility capacity
Statement date
2026-02-08
Promised amount
430.0 MW
Current status
stated

The claim, verbatim

Delta Forge 1, a data center campus in the Southern United States with groundbreaking announced in 2026, is expected to initially support 430 MW of total utility power across two buildings

Source (primary)

Applied Digital 8-K filed 2026-02-09 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “the Company has already announced groundbreaking at another data center campus in the Southern United States ("Delta Forge 1") that is expected to initially support 430 MW of total utility power across two buildings”

How we checked this

Attempted on September 16, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315226005788/form8-k.htm) in full (23,229 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital 8-K filed 2026-02-09

Quote: “the Company has already announced groundbreaking at another data center campus in the Southern United States ("Delta Forge 1") that is expected to initially support 430 MW of total utility power across two buildings”

View cached copy (2026-08-31)Live source ↗