jain.com

Corsicana 910 MW critical IT capacity for Anthropic

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2026-11-18
Promised amount
910.0 MW
Current status
stated

The claim, verbatim

Corsicana will supply 910 MW of critical IT capacity to Anthropic, delivered in phases.

Source (primary)

What Riot’s (RIOT) Anthropic Leases Mean for Its Data Center Buildout - Yahoo Finance (-, news_article)
View cached copy (2026-11-22)Live source ↗Archive.org ↗

Quote: “Riot has agreed to provide Anthropic with 910 megawatts of critical IT capacity”

How we checked this

Checked on November 23, 2026. The cited source supports every part of this claim.

The article states that Riot will provide Anthropic with 910 MW of critical IT capacity at Corsicana, delivered in phases.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/markets/stocks/articles/riot-riot-anthropic-leases-mean-152610583.html) in full (10,689 characters, retrieved November 22, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms What Riot’s (RIOT) Anthropic Leases Mean for Its Data Center Buildout - Yahoo Finance

Quote: “Riot has agreed to provide Anthropic with 910 megawatts of critical IT capacity”

View cached copy (2026-11-22)Live source ↗Archive.org ↗