jain.com

Ellendale crypto mining facility capacity

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2024-09-10
Promised amount
180.0 MW
Current status
stated

The claim, verbatim

180 MW facility in Ellendale North Dakota

Source (primary)

Applied Digital S-1 filed 2024-09-11 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Ellendale, North Dakota: 180 MW facility.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Applied Digital S-1 filed 2024-09-11

Quote: “Ellendale, North Dakota: 180 MW facility.”

View cached copy (2026-08-31)Live source ↗