jain.com

Ellendale, ND data center capacity

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2024-10-03
Promised amount
180.0 MW
Current status
stated

The claim, verbatim

180 MW facility in Ellendale, North Dakota

Source (primary)

Applied Digital S-1 filed 2024-10-04 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “Ellendale, North Dakota: 180 MW facility.”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315224039591/forms-1.htm) in full (130,138 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1 filed 2024-10-04

Quote: “Ellendale, North Dakota: 180 MW facility.”

View cached copy (2026-08-31)Live source ↗