jain.com

Muskogee critical IT capacity

Company: Core Scientific - Project: Muskogee

Subject kind
facility capacity
Statement date
2026-11-19
Promised amount
70.0 MW
Current status
stated

The claim, verbatim

Of the Muskogee facility's 100 MW, approximately 70 MW will serve critical IT equipment for NVIDIA GPU computing, with the remaining 30 MW for cooling, electrical and supporting systems.

Source (primary)

Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review (-, news_article)
View cached copy (2026-11-20)Live source ↗Archive.org ↗

Quote: “Of its 100 MW total power capacity, approximately 70 MW will serve critical IT equipment, with the remaining 30 MW allocated to cooling, electrical systems and other supporting infrastructure”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The article states the 70 MW / 30 MW split and says the 70 MW of critical IT capacity is for NVIDIA GPU computing.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://constructionreviewonline.com/core-scientifics-100-mw-muskogee-ai-data-center-advances-under-8-7b-coreweave-deal/) in full (14,910 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Core Scientific's 100-MW Muskogee AI Data Center Advances Under $8.7B CoreWeave Deal - Construction Review

Quote: “Of its 100 MW total power capacity, approximately 70 MW will serve critical IT equipment, with the remaining 30 MW allocated to cooling, electrical systems and other supporting infrastructure”

View cached copy (2026-11-20)Live source ↗Archive.org ↗