Corsicana 310 MW delivery
Company: Riot - Project: Corsicana
The claim, verbatim
Riot is to deliver the final 310 MW of the Corsicana lease in July 2028.
Source (primary)
Riot Just Signed a $28 Billion AI Lease. September 2027 Is When the Rent Starts - TIKR.com (-, news_article)
View cached copy (2026-11-20)Live source ↗Archive.org ↗
Quote: “310 MW in July 2028”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The article's schedule lists 310 MW in July 2028 as the last of three tranches that together total 910 MW.
Confirmed in the source:
- 310 MW of the Corsicana lease is scheduled for delivery in July 2028
- July 2028 is the final tranche, completing the 910 MW (400 + 200 + 310)
What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/riot-just-signed-a-28-billion-ai-lease-september-2027-is-when-the-rent-starts?) in full (8,089 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot Just Signed a $28 Billion AI Lease. September 2027 Is When the Rent Starts - TIKR.com
Quote: “310 MW in July 2028”