HPC data center facility in Ellendale

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2024-10-22
Promised amount
100.0 MW
Current status
stated

The claim, verbatim

Company broke ground on 100 MW HPC data center project in Ellendale, ND

Source (primary)

Applied Digital S-1 filed 2024-10-23 (SEC EDGAR, sec_filing)
View cached copy (2026-08-31)Live source ↗

Quote: “The Company also broke ground on a 100 MW HPC data center project in Ellendale, ND (the "HPC Ellendale Facility"), on land located adjacent to its existing 180 MW Data center hosting facility.”

How we checked this

Attempted on September 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1144879/000149315224042178/forms-1.htm) in full (127,290 characters, retrieved August 31, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Applied Digital S-1 filed 2024-10-23

Quote: “The Company also broke ground on a 100 MW HPC data center project in Ellendale, ND (the "HPC Ellendale Facility"), on land located adjacent to its existing 180 MW Data center hosting facility.”

View cached copy (2026-08-31)Live source ↗