Corsicana tanks commissioning and Building A1 erection Q4 2023
Company: Riot - Project: Corsicana
What the later record shows
Delivered; the record does not say when
Building A1 was hashing by April 2024 and complete by June 30, 2024, so the tanks and the building plainly exist. No passage dates the tank commissioning or the A1 erection, so the Q4 2023 timing cannot be confirmed.
“The first batch of miners in the first 100 MW building, Building A1, have been installed and are already hashing”
2024-04-17 · riot 8-K exhibit (riot-20240418xex99d1.htm) View cached copy (2026-11-08)Live source ↗
“As of June 30, 2024, the first 100 MW building, Building A1, was completed”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Corsicana timeline calls for tank commissioning and Building A1 erection in Q4 2023.
Source (primary)
riot 8-K exhibit (riot-20230906xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-20)Live source ↗
Quote: “Q4 2023 Tanks Commissioning Q4 2023 Building A1 Erection”
How we checked this
Checked on November 21, 2026. The cited source supports every part of this claim.
The Corsicana timeline lists both 'Q4 2023 Tanks Commissioning' and 'Q4 2023 Building A1 Erection'.
Confirmed in the source:
- The Corsicana timeline calls for tank commissioning in Q4 2023
- The Corsicana timeline calls for Building A1 erection in Q4 2023
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000155837023015517/riot-20230906xex99d2.htm) in full (31,186 characters, retrieved November 20, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20230906xex99d2.htm)
Quote: “Q4 2023 Tanks Commissioning Q4 2023 Building A1 Erection”
confirms Riot 10-Q filed 2024-07-31
Quote: “As of June 30, 2024, the first 100 MW building, Building A1, was completed”
confirms riot 8-K exhibit (riot-20240418xex99d1.htm)
Quote: “The first batch of miners in the first 100 MW building, Building A1, have been installed and are already hashing”