jain.com

CoreWeave leases all 400 MW of Applied Digital's Polaris Forge 1

Company: CoreWeave - Project: Polaris Forge 1

Subject kind
customer
Statement date
2026-11-18
Promised amount
11000000000.0 USD
Current status
stated

The claim, verbatim

CoreWeave leased all 400 MW of Applied Digital's Polaris Forge 1 campus in North Dakota on a 15-year take-or-pay lease worth about $11.0 billion over its base term.

Source (primary)

Forget CoreWeave: Applied Digital Is the Real Loser as “The Bank of Nvidia” Pulls Back - TIKR.com (-, news_article)
View cached copy (2026-11-19)Live source ↗Archive.org ↗

Quote: “Applied Digital leased all 400 MW of its Polaris Forge 1 campus in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term.”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The article says Applied Digital leased all 400 MW of Polaris Forge 1 in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion, which is the same arrangement stated from the tenant's side.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/forget-coreweave-applied-digital-is-the-real-loser-as-the-bank-of-nvidia-pulls-back) in full (7,834 characters, retrieved November 19, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Forget CoreWeave: Applied Digital Is the Real Loser as “The Bank of Nvidia” Pulls Back - TIKR.com

Quote: “Applied Digital leased all 400 MW of its Polaris Forge 1 campus in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term.”

View cached copy (2026-11-19)Live source ↗Archive.org ↗