Applied Digital leased all 400 MW of its Polaris Forge 1 campus in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term.

Source (primary)

Forget CoreWeave: Applied Digital Is the Real Loser as “The Bank of Nvidia” Pulls Back - TIKR.com (-, news_article)
View cached copy (2026-11-19)Live source ↗Archive.org ↗

Quote: “Applied Digital leased all 400 MW of its Polaris Forge 1 campus in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term”

How we checked this

Checked on November 21, 2026. The cited source supports every part of this claim.

The article states that Applied Digital leased all 400 MW of its North Dakota Polaris Forge 1 campus to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.tikr.com/blog/forget-coreweave-applied-digital-is-the-real-loser-as-the-bank-of-nvidia-pulls-back) in full (7,834 characters, retrieved November 19, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Forget CoreWeave: Applied Digital Is the Real Loser as “The Bank of Nvidia” Pulls Back - TIKR.com

Quote: “Applied Digital leased all 400 MW of its Polaris Forge 1 campus in North Dakota to CoreWeave on a 15-year take-or-pay lease worth about $11.0 billion over its base term”