Corsicana second batch of miners online
Company: Riot - Project: Corsicana
What the later record shows
Delivered; the record does not say when
The 2024 10-K says Phase I at Corsicana was completed during 2024, with 400 MW developed and 14.1 EH/s deployed by year-end. That implies miners beyond the first batch came online. No passage dates a 'second batch', so whether it met Q2 2024 cannot be determined.
“During 2024, we completed Phase I of development of the Corsicana Facility, a second large-scale Bitcoin mining facility, currently equipped to provide up to 400 megawatts”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“Delivery of these miners began in 2023, and all miners under these purchase orders are expected to be received through the end of 2026, with deployment continuing on an ongoing basis.”
2026-11-03 · Riot 10-Q filed 2026-11-04 View cached copy (2026-11-05)Live source ↗
Checked November 16, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot expects the second batch of miners at the Corsicana Facility to come online in Q2 2024.
Source (primary)
riot 8-K exhibit (riot-20231204xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗
Quote: “Q2 2024 Second Batch of Miners Online”
How we checked this
Additional evidence
confirms riot 8-K exhibit (riot-20231204xex99d2.htm)
Quote: “Q2 2024 Second Batch of Miners Online”
confirms Riot 10-K filed 2025-02-28
Quote: “During 2024, we completed Phase I of development of the Corsicana Facility, a second large-scale Bitcoin mining facility, currently equipped to provide up to 400 megawatts”
confirms Riot 10-Q filed 2026-11-04
Quote: “Delivery of these miners began in 2023, and all miners under these purchase orders are expected to be received through the end of 2026, with deployment continuing on an ongoing basis.”