jain.com

Blockchain data centers combined capacity

Company: Applied Digital - Project: Ellendale

Subject kind
facility capacity
Statement date
2024-01-16
Promised amount
480.0 MW
Current status
stated

The claim, verbatim

The company has three blockchain data centers with a combined capacity of 480MW: Garden City, TX (200MW), Jamestown, ND (100MW) and Ellendale, ND (180MW).

Source (primary)

applied-digital 8-K exhibit (applieddigital-investorp.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-14)Live source ↗

Quote: “The Company has three Blockchain Data Centers with a combined capacity of 480MWs.”

How we checked this

Attempted on November 17, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000012/applieddigital-investorp.htm) in full (14,133 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms applied-digital 8-K exhibit (applieddigital-investorp.htm)

Quote: “The Company has three Blockchain Data Centers with a combined capacity of 480MWs.”

View cached copy (2026-11-14)Live source ↗