jain.com

Corsicana potential build-out

Company: Riot - Project: Corsicana

Subject kind
facility capacity
Statement date
2026-11-09
Promised amount
672.0 MW
Current status
stated

The claim, verbatim

After acquiring a further 238 acres, the Corsicana site could total 11 buildings and 672MW, with potential to expand to 1GW.

Source (primary)

Riot Platforms signs 910MW agreement with unnamed frontier AI lab (-, news_article)
View cached copy (2026-11-10)Live source ↗Archive.org ↗

Quote: “it was said to potentially total 11 buildings and 672MW, with potential to expand further to 1GW”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The article reports the land acquisition and the potential build-out figures stated at that time.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.datacenterdynamics.com/en/news/riot-platforms-signs-910mw-agreement-with-unnamed-frontier-ai-lab/) in full (8,709 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot Platforms signs 910MW agreement with unnamed frontier AI lab

Quote: “it was said to potentially total 11 buildings and 672MW, with potential to expand further to 1GW”

View cached copy (2026-11-10)Live source ↗Archive.org ↗

confirms Riot Platforms signs 910MW agreement with unnamed frontier AI lab - Data Center Dynamics

Quote: “it was said to potentially total 11 buildings and 672MW, with potential to expand further to 1GW”

View cached copy (2026-11-10)Live source ↗Archive.org ↗