Corsicana two-story data center build
Company: Riot - Project: Corsicana
The claim, verbatim
Riot is building a new 335,430 sq ft two-story data center at Corsicana as a $400 million project, with development running from April 2026 to May 2028.
Source (primary)
Riot Platforms signs 910MW agreement with unnamed frontier AI lab (-, news_article)
View cached copy (2026-11-10)Live source ↗Archive.org ↗
Quote: “Development on the $400 million project is set to run from April 2026 to May 2028.”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The article states the building's size and height, the project cost and the development dates.
Confirmed in the source:
- Riot is building a new two-story data center at the Corsicana site
- The data center totals 335,430 sq ft
- It is a $400 million project
- Development is set to run from April 2026 to May 2028
What we did: Read our cached copy of the publisher (https://www.datacenterdynamics.com/en/news/riot-platforms-signs-910mw-agreement-with-unnamed-frontier-ai-lab/) in full (8,709 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Riot Platforms signs 910MW agreement with unnamed frontier AI lab
Quote: “Development on the $400 million project is set to run from April 2026 to May 2028.”
confirms Riot Platforms signs 910MW agreement with unnamed frontier AI lab - Data Center Dynamics
Quote: “Development on the $400 million project is set to run from April 2026 to May 2028.”