Corsicana Phase II buildings online by end-2025
Company: Riot - Project: Corsicana
What the later record shows
The date slipped
Corsicana's developed capacity was still 400 MW at December 31, 2025, unchanged from a year earlier and equal to the completed 400 MW Phase I, which indicates the Phase II buildings were not online when due. No passage names a new date or says Phase II was cancelled.
“During 2024, we completed the 400 MW Phase I of development of the Corsicana Facility.”
2025-04-30 · Riot 10-Q filed 2025-05-01 View cached copy (2026-08-31)Live source ↗
“Corsicana Facility 400 400 Kentucky Facility 192 60 Total power capacity 1,292 1,160”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Phase II of the Corsicana Facility will bring two additional buildings online by the end of 2025.
Source (primary)
riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗
Quote: “Phase II of the Corsicana Facility will bring two additional buildings online by the end of 2025”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The release states this plan directly.
Confirmed in the source:
- Phase II of the Corsicana Facility was planned to bring two additional buildings online by the end of 2025.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240222xex99d1.htm)
Quote: “Phase II of the Corsicana Facility will bring two additional buildings online by the end of 2025”
delays Riot 10-Q filed 2025-05-01
Quote: “During 2024, we completed the 400 MW Phase I of development of the Corsicana Facility.”
delays Riot 10-K filed 2026-03-02
Quote: “Corsicana Facility 400 400 Kentucky Facility 192 60 Total power capacity 1,292 1,160”