Corsicana Buildings B1 & B2 online

Company: Riot - Project: Corsicana

Subject kind
facility timeline
Statement date
2024-02-22
Promised by
2024-12-31
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

Building B1 was operational by September 30, 2024, with B2 still under construction. Corsicana's developed capacity reached 400 MW as of December 31, 2024, which implies all four 100 MW buildings were done, although no passage names B2 as complete.

“three operational buildings, Buildings A1, A2 and B1, and a fourth building, Building B2, which was under construction”
2024-11-03 · Riot 10-Q filed 2024-11-04 View cached copy (2026-08-31)Live source ↗
“Corsicana Facility ​ ​ 400 ​ ​ — ​ ​ — Kentucky Facility ​ ​ 60 ​ ​ — ​ ​ — Total power capacity ​ ​ 1,160”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗

Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Corsicana Buildings B1 and B2 are expected to be brought online during the third and fourth quarters of 2024.

Source (primary)

riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗

Quote: “with Buildings B1 & B2 being brought online during the third and fourth quarters of 2024”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The release states this expected timing directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms riot 8-K exhibit (riot-20240222xex99d1.htm)

Quote: “with Buildings B1 & B2 being brought online during the third and fourth quarters of 2024”

View cached copy (2026-11-10)Live source ↗

confirms Riot 10-Q filed 2024-11-04

Quote: “three operational buildings, Buildings A1, A2 and B1, and a fourth building, Building B2, which was under construction”

View cached copy (2026-08-31)Live source ↗

confirms Riot 10-K filed 2025-02-28

Quote: “Corsicana Facility ​ ​ 400 ​ ​ — ​ ​ — Kentucky Facility ​ ​ 60 ​ ​ — ​ ​ — Total power capacity ​ ​ 1,160”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 10, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.