Corsicana Building A2 online

Company: Riot - Project: Corsicana

Subject kind
facility timeline
Statement date
2024-02-22
Promised by
2024-06-30
Current status
verified

What the later record shows

Delivered late · happened September 30, 2024

Building A2 was still only nearly complete as of June 30, 2024, and it is reported completed as of September 30, 2024. The September date is an upper bound on when it finished.

“the second 100 MW building, Building A2, was nearly complete with nearly all immersion tanks and miners in the building being operational”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
“As of September 30, 2024, Corsicana deployed 300 MW of Bitcoin mining infrastructure comprised of three 100 MW buildings, Buildings A1, A2 and B1, which were completed”
2024-11-03 · Riot 10-Q filed 2024-11-04 View cached copy (2026-08-31)Live source ↗

Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Corsicana Building A2 is expected to be completed and brought online towards the end of Q2 2024.

Source (primary)

riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗

Quote: “Building A2 is expected to be completed and brought online towards the end of Q2 2024”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The release states this expected timing directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms riot 8-K exhibit (riot-20240222xex99d1.htm)

Quote: “Building A2 is expected to be completed and brought online towards the end of Q2 2024”

View cached copy (2026-11-10)Live source ↗

confirms Riot 10-Q filed 2024-07-31

Quote: “the second 100 MW building, Building A2, was nearly complete with nearly all immersion tanks and miners in the building being operational”

View cached copy (2026-08-31)Live source ↗

confirms Riot 10-Q filed 2024-11-04

Quote: “As of September 30, 2024, Corsicana deployed 300 MW of Bitcoin mining infrastructure comprised of three 100 MW buildings, Buildings A1, A2 and B1, which were completed”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 10, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 10, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 10, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.