Corsicana Building A2 online
Company: Riot - Project: Corsicana
What the later record shows
Delivered late · happened September 30, 2024
Building A2 was still only nearly complete as of June 30, 2024, and it is reported completed as of September 30, 2024. The September date is an upper bound on when it finished.
“the second 100 MW building, Building A2, was nearly complete with nearly all immersion tanks and miners in the building being operational”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
“As of September 30, 2024, Corsicana deployed 300 MW of Bitcoin mining infrastructure comprised of three 100 MW buildings, Buildings A1, A2 and B1, which were completed”
2024-11-03 · Riot 10-Q filed 2024-11-04 View cached copy (2026-08-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Corsicana Building A2 is expected to be completed and brought online towards the end of Q2 2024.
Source (primary)
riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗
Quote: “Building A2 is expected to be completed and brought online towards the end of Q2 2024”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The release states this expected timing directly.
Confirmed in the source:
- Corsicana Building A2 was expected to be completed and brought online towards the end of Q2 2024.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240222xex99d1.htm)
Quote: “Building A2 is expected to be completed and brought online towards the end of Q2 2024”
confirms Riot 10-Q filed 2024-07-31
Quote: “the second 100 MW building, Building A2, was nearly complete with nearly all immersion tanks and miners in the building being operational”
confirms Riot 10-Q filed 2024-11-04
Quote: “As of September 30, 2024, Corsicana deployed 300 MW of Bitcoin mining infrastructure comprised of three 100 MW buildings, Buildings A1, A2 and B1, which were completed”