Corsicana A1 miners brought online
Company: Riot - Project: Corsicana
What the later record shows
Delivered late · happened June 30, 2024
On April 30, 2024 only the first batch was hashing and deployment in Building A1 was still continuing. The building is first reported complete as of June 30, 2024, so that date is an upper bound on when it finished.
“miners will continue to be deployed in Building A1 until a total capacity of 3.7 EH/s is reached”
2024-04-30 · riot 8-K exhibit (riot-20240501xex99d1.htm) View cached copy (2026-11-08)Live source ↗
“As of June 30, 2024, the first 100 MW building, Building A1, was completed”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Miners at Corsicana Building A1 will be brought online in batches over the first several weeks of April 2024.
Source (primary)
riot 8-K exhibit (riot-20240222xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗
Quote: “Miners will be brought online in batches over the first several weeks of April 2024.”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The release states this timing immediately after describing the energization of Building A1, so the miners sentence refers to that building.
Confirmed in the source:
- Miners at Corsicana Building A1 were planned to be brought online in batches.
- The planned timing was the first several weeks of April 2024.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d1.htm) in full (21,844 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240222xex99d1.htm)
Quote: “Miners will be brought online in batches over the first several weeks of April 2024.”
confirms Riot 10-Q filed 2024-07-31
Quote: “As of June 30, 2024, the first 100 MW building, Building A1, was completed”
confirms riot 8-K exhibit (riot-20240501xex99d1.htm)
Quote: “miners will continue to be deployed in Building A1 until a total capacity of 3.7 EH/s is reached”