Corsicana facility energization
Company: Riot - Project: Corsicana
What the later record shows
Delivered; the record does not say when
The Corsicana substation was described as recently energized on April 30, 2024, and operations began in April 2024 after that energization. No passage says whether energization occurred by March 31, 2024.
“The recently energized substation will power the initial 400 MW phase of development of the Corsicana Facility.”
2024-04-30 · riot 8-K exhibit (riot-20240501xex99d1.htm) View cached copy (2026-11-08)Live source ↗
“Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”
2024-07-30 · Riot 10-Q filed 2024-07-31 View cached copy (2026-08-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot expects its new large-scale facility to be energized in Q1 2024.
Source (primary)
riot 8-K exhibit (riot-20240222xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗
Quote: “New Large-Scale Facility Energized in Q1 2024”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The presentation, dated before the end of Q1 2024, lists New Large-Scale Facility Energized in Q1 2024, which matches the claim as worded.
Confirmed in the source:
- Riot's February 22, 2024 presentation indicates a new large-scale facility energized in Q1 2024
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000001/riot-20240222xex99d2.htm) in full (20,192 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240222xex99d2.htm)
Quote: “New Large-Scale Facility Energized in Q1 2024”
confirms Riot 10-Q filed 2024-07-31
Quote: “Operations of this initial phase of the development commenced in April 2024, following energization of the substation.”
confirms riot 8-K exhibit (riot-20240501xex99d1.htm)
Quote: “The recently energized substation will power the initial 400 MW phase of development of the Corsicana Facility.”