MicroBT second order deliveries
Company: Riot - Project: Corsicana
What the later record shows
Outcome not yet confirmed
The only later passage restates the plan as a forecast: all 99,840 miners from both orders are expected by mid-2025. No passage confirms that the second order of 66,560 miners was fully delivered, or when.
“All 99,840 miners are expected to be received and deployed by mid-2025.”
2024-08-08 · riot 8-K exhibit (riot-20231231xex99d1.htm) View cached copy (2026-10-31)Live source ↗
Checked November 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot placed a second order of 66,560 MicroBT miners at $16/TH for the next four Corsicana buildings, with $223 million remaining on the order and deliveries scheduled through April 2025.
Source (primary)
riot 8-K exhibit (riot-20240224xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗
Quote: “Includes remaining $223 million on second order of 66,560 additional miners scheduled to be delivered through April 2025”
How we checked this
Checked on November 11, 2026. The cited source supports every part of this claim.
The MicroBT order slide and the funding slide's footnote together establish every detail of the claim.
Confirmed in the source:
- Riot's second MicroBT order was for 66,560 miners
- The second order was priced at $16/TH
- The second order was for the next four buildings at the Corsicana facility
- $223 million remained on the second order
- The second order's miners were scheduled to be delivered through April 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000116741924000008/riot-20240224xex99d2.htm) in full (20,494 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240224xex99d2.htm)
Quote: “Includes remaining $223 million on second order of 66,560 additional miners scheduled to be delivered through April 2025”