jain.com

Austin TX data center capacity for CoreWeave

Company: Core Scientific - Project: Austin Data Center (ASDC)

Subject kind
facility capacity
Statement date
2024-03-05
Promised amount
16.0 MW
Current status
stated

The claim, verbatim

Core Scientific will deliver up to 16 MW of capacity at its new Austin, TX data center to host CoreWeave's infrastructure.

Source (primary)

core-scientific 8-K exhibit (finalcorzcoreweaverelease0.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗

Quote: “Core Scientific will deliver up to 16 MW of capacity at its new Austin, TX data center to host CoreWeave’s infrastructure”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The press release states the 16 MW maximum, the new Austin, Texas location, and the purpose of hosting CoreWeave's infrastructure.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1839341/000162828024009396/finalcorzcoreweaverelease0.htm) in full (8,248 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms core-scientific 8-K exhibit (finalcorzcoreweaverelease0.htm)

Quote: “Core Scientific will deliver up to 16 MW of capacity at its new Austin, TX data center to host CoreWeave’s infrastructure”

View cached copy (2026-11-09)Live source ↗