NC-2/NC-3 initial ready-for-service in late 2027
Company: WhiteFiber - Project: NC-2 and NC-3
The claim, verbatim
WhiteFiber is targeting initial ready-for-service capacity at NC-2 and NC-3 in late 2027, dependent on infrastructure, customer commitments, financing, and approvals.
Source (primary)
WhiteFiber Acquires Two North Carolina Data Center Properties For $60 Million With Potential For 200 MW Of Capacity - Pulse 2.0 (-, news_article)
View cached copy (2026-11-08)Live source ↗Archive.org ↗
Quote: “WhiteFiber is targeting initial ready-for-service capacity at NC-2 and NC-3 in late 2027.”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The article gives the late-2027 target and says the schedule depends on infrastructure, customer commitments, financing, and approvals.
Confirmed in the source:
- WhiteFiber is targeting initial ready-for-service capacity at NC-2 and NC-3 in late 2027.
- The schedule depends on obtaining necessary infrastructure, customer commitments, financing, and other project approvals.
What we did: Read our cached copy of the publisher (https://pulse2.com/whitefiber-acquires-two-north-carolina-data-center-properties-for-60-million-with-potential-for-200-mw-of-capacity/) in full (5,359 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms WhiteFiber Acquires Two North Carolina Data Center Properties For $60 Million With Potential For 200 MW Of Capacity - Pulse 2.0
Quote: “WhiteFiber is targeting initial ready-for-service capacity at NC-2 and NC-3 in late 2027.”