Corsicana final phase (310 MW) delivery

Company: Riot - Project: Corsicana

Subject kind
facility timeline
Statement date
2026-11-04
Promised by
2028-07-31
Promised amount
310.0 MW
Current status
stated

The claim, verbatim

The final 310 MW at Corsicana is due in July 2028.

Source (primary)

Riot's $28B Lease Shows Why Location and Contracts Matter in AI - Yahoo Finance (-, news_article)
View cached copy (2026-11-08)Live source ↗Archive.org ↗

Quote: “and the final 310 MW in July 2028”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The article states that Corsicana's phases are 400 MW in September 2027, 200 MW in January 2028, and the final 310 MW in July 2028, which matches the claim.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/riots-28b-lease-shows-why-134500229.html) in full (14,262 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Riot's $28B Lease Shows Why Location and Contracts Matter in AI - Yahoo Finance

Quote: “and the final 310 MW in July 2028”

View cached copy (2026-11-08)Live source ↗Archive.org ↗