Ellendale hosting restored to 65%-75% by end of May 2024
Company: Applied Digital - Project: Ellendale
What the later record shows
Outcome not yet confirmed
On April 28, 2024 Ellendale was at about 80 MW (roughly 44% of 180 MW), and the company only reaffirmed the 65%-75% target. No later passage says whether the target was reached by the end of May 2024.
“The company confirms that it expects the Ellendale facility to be operating at 65% to 75% of capacity by the end of its current fiscal year.”
2024-04-28 · Applied Digital 8-K filed 2024-04-29 View cached copy (2026-08-31)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
As new transformers are received and installed, the company targets operating the 180 MW Ellendale hosting facility at approximately 65%-75% of full capacity by the end of May 2024.
Source (primary)
applied-digital 8-K exhibit (apld3q24earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “the Ellendale facility will target operating capacity of approximately 65%-75% of full capacity by the end of May 2024”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The release says that as new transformers are received and installed, the 180 MW Ellendale facility will target about 65%-75% of full capacity by the end of May 2024.
Confirmed in the source:
- The Ellendale hosting facility is 180 MW
- The company targets about 65%-75% of full capacity by the end of May 2024
- The target depends on new transformers being received and installed
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1144879/000114487924000077/apld3q24earningsrelease.htm) in full (28,454 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms applied-digital 8-K exhibit (apld3q24earningsrelease.htm)
Quote: “the Ellendale facility will target operating capacity of approximately 65%-75% of full capacity by the end of May 2024”