Corsicana 1 GW development / 400 MW substation
Company: Riot - Project: Corsicana
The claim, verbatim
Riot is developing a 1 GW facility in Corsicana, Texas, served by a 400 MW substation, with a Phase 1 400 MW build-out and an additional 200 MW build-out planned.
Source (primary)
riot 8-K exhibit (riot-20240501xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “1 GW Corsicana Facility Development – Corsicana, Texas”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The presentation refers to the '1 GW Corsicana Facility Development – Corsicana, Texas,' a '400 MW Substation at Corsicana Facility,' the 'Phase 1 400MW Corsicana build-out,' and a 'Corsicana Facility additional 200 MW build-out' in its funded capital plans.
Confirmed in the source:
- Riot is developing a 1 GW facility in Corsicana, Texas
- The Corsicana Facility has a 400 MW substation
- Riot has a Phase 1 400 MW build-out at Corsicana
- Riot plans an additional 200 MW build-out at the Corsicana Facility
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000155837024006323/riot-20240501xex99d2.htm) in full (23,476 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240501xex99d2.htm)
Quote: “1 GW Corsicana Facility Development – Corsicana, Texas”