Corsicana miner deployment complete by H2 2025
Company: Riot - Project: Corsicana
What the later record shows
Outcome not yet confirmed
Corsicana's deployed hash rate plateaued at 15.7 EH/s through 2025, which is consistent with deployment being finished. No passage states that Corsicana miner deployment was completed; filings still describe it as expected by mid-2025.
“Delivery of these miners began in 2023 and all miners are expected to be received and deployed by mid-2025.”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Deployment of miners intended for the Corsicana Facility has begun and is estimated to be completed by the second half of 2025.
Source (primary)
riot 8-K exhibit (riot-20240501xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗
Quote: “Deployment of these miners intended for the Corsicana Facility has begun and is estimated to be completed by the second half of 2025.”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The release states that Corsicana deployment has begun and is estimated to finish by the second half of 2025.
Confirmed in the source:
- Deployment of miners intended for the Corsicana Facility has begun
- Corsicana miner deployment is estimated to be completed by the second half of 2025
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1167419/000155837024006323/riot-20240501xex99d1.htm) in full (16,711 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms riot 8-K exhibit (riot-20240501xex99d1.htm)
Quote: “Deployment of these miners intended for the Corsicana Facility has begun and is estimated to be completed by the second half of 2025.”