Ellendale HPC main substation transformer energized
Company: Applied Digital
The claim, verbatim
The company energized the on-site main substation transformer at its purpose-built HPC data center in Ellendale, ND.
Source (primary)
applied-digital 8-K exhibit (apldq225earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-21)Live source ↗
Quote: “Successfully energized the on-site main substation transformer at the purpose-built HPC data center in Ellendale, ND”