Corsicana substation expansion +600 MW

Company: Riot

This claim was marked delayed on October 19, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2025-02-23
Promised by
2026-03-31
Promised amount
600.0 MW
Current status
delayed

What the later record shows

The date slipped

Corsicana developed power capacity was still 400 MW at March 31, 2026, and substation capex was still being spent in Q4 2025. No passage says the added 600 MW came online by early 2026, but the developed-capacity metric may not capture substation power.

“Corsicana 600MW Substation $52.7 million $12.9 million”
2025-10-29 · riot 8-K exhibit (riot-20251030xex99d2.htm) View cached copy (2026-09-27)Live source ↗
“Corsicana Facility ​ ​ 400 ​ ​ 400 Kentucky Facility ​ ​ 162 ​ ​ 65 Total power capacity ​ ​ 1,262 ​ ​ 1,165”
2026-04-29 · Riot 10-Q filed 2026-04-30 View cached copy (2026-08-31)Live source ↗

Checked October 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Riot is developing and expanding the Corsicana substation, which is expected to add 600 MW of additional power capacity by early 2026, bringing the site to 1,000 MW.

Source (primary)

riot 8-K exhibit (riot-20250224xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗

Quote: “Riot continues to develop and expand the substation at Corsicana which is expected to add 600 MW of additional power capacity by early 2026”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20250224xex99d2.htm)

Quote: “Riot continues to develop and expand the substation at Corsicana which is expected to add 600 MW of additional power capacity by early 2026”

View cached copy (2026-10-19)Live source ↗

delays Riot 10-Q filed 2026-04-30

Quote: “Corsicana Facility ​ ​ 400 ​ ​ 400 Kentucky Facility ​ ​ 162 ​ ​ 65 Total power capacity ​ ​ 1,262 ​ ​ 1,165”

View cached copy (2026-08-31)Live source ↗

delays riot 8-K exhibit (riot-20251030xex99d2.htm)

Quote: “Corsicana 600MW Substation $52.7 million $12.9 million”

View cached copy (2026-09-27)Live source ↗

Record of changes

October 19, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 19, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.