Corsicana substation expansion +600 MW
Company: Riot
What the later record shows
The date slipped
Corsicana developed power capacity was still 400 MW at March 31, 2026, and substation capex was still being spent in Q4 2025. No passage says the added 600 MW came online by early 2026, but the developed-capacity metric may not capture substation power.
“Corsicana 600MW Substation $52.7 million $12.9 million”
2025-10-29 · riot 8-K exhibit (riot-20251030xex99d2.htm) View cached copy (2026-09-27)Live source ↗
“Corsicana Facility 400 400 Kentucky Facility 162 65 Total power capacity 1,262 1,165”
2026-04-29 · Riot 10-Q filed 2026-04-30 View cached copy (2026-08-31)Live source ↗
Checked October 19, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot is developing and expanding the Corsicana substation, which is expected to add 600 MW of additional power capacity by early 2026, bringing the site to 1,000 MW.
Source (primary)
riot 8-K exhibit (riot-20250224xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗
Quote: “Riot continues to develop and expand the substation at Corsicana which is expected to add 600 MW of additional power capacity by early 2026”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20250224xex99d2.htm)
Quote: “Riot continues to develop and expand the substation at Corsicana which is expected to add 600 MW of additional power capacity by early 2026”
delays Riot 10-Q filed 2026-04-30
Quote: “Corsicana Facility 400 400 Kentucky Facility 162 65 Total power capacity 1,262 1,165”
delays riot 8-K exhibit (riot-20251030xex99d2.htm)
Quote: “Corsicana 600MW Substation $52.7 million $12.9 million”