Hunt County energization 2027, full power by 2029

Company: Core Scientific - Project: Hunt County

Subject kind
facility timeline
Statement date
2026-03-02
Promised by
2029-12-31
Promised amount
430.0 MW
Current status
stated

The claim, verbatim

The Hunt County site is expected to begin energization in 2027 and ramp to full power by 2029, with power and ramp schedule approved through ERCOT interconnection in October 2024.

Source (primary)

Fourth Quarter Fiscal Year 2025 Earnings Presentation (IR page (investors.corescientific.com), ir_presentation)
View cached copy (2026-10-16)Live source ↗Archive.org ↗

Quote: “Begin energization in 2027, ramping to full power by 2029”

How we checked this

Checked on October 17, 2026. The cited source supports part of this claim, but not all of it.

The timeline and ERCOT approval appear on the Hunt County slide, but the layout makes it unclear whether they describe Hunt County or Pecos.

Confirmed in the source:

We could not confirm this from the cited source:

That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.

What we did: Read our cached copy of IR page (investors.corescientific.com) (https://d1io3yog0oux5.cloudfront.net/_b76ddaa46c59e7a64138659274ff5f32/corescientific/db/1066/11266/pdf/Q4+FY25+earnings+deck+vfinal.2+PDF.pdf) in full (13,731 characters, retrieved October 16, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Fourth Quarter Fiscal Year 2025 Earnings Presentation

Quote: “Begin energization in 2027, ramping to full power by 2029”