jain.com

Taloja campus expansion potential to 480 MW

Company: CoreWeave - Project: Taloja Campus

Subject kind
facility capacity
Statement date
2026-10-08
Promised amount
480.0 MW
Current status
stated

The claim, verbatim

The campus has potential to double capacity by another 240 MW, for a possible total of 480 MW.

Source (primary)

CoreWeave Makes a 240 MW Bet on India's AI Infrastructure - Yahoo Finance (-, news_article)
View cached copy (2026-10-09)Live source ↗

Quote: “The campus also has the potential to double capacity by another 240 MW, giving the company a possible total expansion opportunity of 480 MW”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The article says the campus could double by another 240 MW, for a possible total of 480 MW.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/coreweave-makes-240-mw-bet-115600863.html) in full (11,529 characters, retrieved October 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CoreWeave Makes a 240 MW Bet on India's AI Infrastructure - Yahoo Finance

Quote: “The campus also has the potential to double capacity by another 240 MW, giving the company a possible total expansion opportunity of 480 MW”

View cached copy (2026-10-09)Live source ↗