Option to expand Taloja capacity to 480 MW
Company: CoreWeave - Project: Taloja Campus
The claim, verbatim
CoreWeave has an option to expand its capacity at the Taloja campus to 480 MW.
Source (primary)
CoreWeave Plans First India Data Centres Through AdaniConneX Partnership - Yahoo Finance (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “with an option to expand capacity to 480 megawatts”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article says CoreWeave's 240 MW at the Taloja campus comes with an option to expand capacity to 480 megawatts.
Confirmed in the source:
- CoreWeave has an option to expand its capacity at the Taloja campus
- The expansion option would take capacity to 480 MW
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/coreweave-plans-first-india-data-123521521.html) in full (7,672 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CoreWeave Plans First India Data Centres Through AdaniConneX Partnership - Yahoo Finance
Quote: “with an option to expand capacity to 480 megawatts”
confirms CoreWeave Locks In 240 MW In India With AdaniConneX Data Center Deal As AI Cloud Provider Ramps Up Global Buildout - Yahoo Finance
Quote: “with an option to double that amount to 480 megawatts”