The claim, verbatim
CoreWeave will have the opportunity to double capacity by expanding by up to an additional 240 megawatts at the Taloja campus.
Source (primary)
CoreWeave enters India with 240MW AI cloud expansion at AdaniConneX campus - ROI-NJ (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “will have the opportunity to double capacity by expanding by up to an additional 240 megawatts at the campus”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article states that CoreWeave can double capacity by expanding by up to an additional 240 megawatts at the campus.
Confirmed in the source:
- CoreWeave will have the opportunity to double capacity at the Taloja campus
- The expansion option is for up to an additional 240 megawatts
What we did: Read our cached copy of the publisher (https://www.roi-nj.com/2026/10/07/tech/coreweave-enters-india-with-240mw-ai-cloud-expansion-at-adaniconnex-campus/) in full (12,296 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CoreWeave enters India with 240MW AI cloud expansion at AdaniConneX campus - ROI-NJ
Quote: “will have the opportunity to double capacity by expanding by up to an additional 240 megawatts at the campus”