Taloja campus expansion option
Company: CoreWeave - Project: Taloja Campus
The claim, verbatim
CoreWeave has an option to expand capacity at the Taloja campus to 480 MW.
Source (primary)
CoreWeave expands to India with Adani data center venture - Yahoo Finance (-, news_article)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “with an option to expand to 480 megawatts”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The article says the 240 MW at Taloja comes with an option to expand to 480 megawatts.
Confirmed in the source:
- CoreWeave has an option to expand its Taloja campus capacity to 480 MW
What we did: Read our cached copy of the publisher (https://finance.yahoo.com/technology/ai/articles/coreweave-expands-india-adani-data-122038847.html) in full (8,061 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CoreWeave expands to India with Adani data center venture - Yahoo Finance
Quote: “with an option to expand to 480 megawatts”
confirms CoreWeave Plans First India Data Centres Through AdaniConneX Partnership - Yahoo Finance
Quote: “with an option to expand capacity to 480 megawatts”