Delta Forge 1 capacity
Company: Applied Digital - Project: Delta Forge 1
The claim, verbatim
Delta Forge 1 is a 430 MW AI Factory campus designed to deliver up to 300 MW of critical IT load. The filing gives the site size inconsistently, as more than 500 acres in one place and more than 600 acres in another.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-08)Live source ↗Archive.org ↗
Quote: “designed to deliver up to 300 MW of critical IT load for high-density AI workloads”
How we checked this
Checked on October 13, 2026. The cited source supports every part of this claim.
The Recent Highlights section calls Delta Forge 1 a 430 MW campus of more than 500 acres designed for up to 300 MW of critical IT load. The Management Commentary and HPC Hosting Update sections describe it as spanning more than 600 acres, which confirms the inconsistency the claim notes.
Confirmed in the source:
- Delta Forge 1 is described as a 430 MW AI Factory campus
- Delta Forge 1 is designed to deliver up to 300 MW of critical IT load
- The release describes the Delta Forge 1 site as spanning more than 500 acres in one place
- The release describes the Delta Forge 1 site as spanning more than 600 acres in other places, so the site size is stated inconsistently
What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/148/applied-digital-reports-fiscal-third-quarter-2026-results/) in full (47,470 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Earnings Release
Quote: “designed to deliver up to 300 MW of critical IT load for high-density AI workloads”