Ellendale ND facility – full 180MW online

Company: Applied Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2023-04-06
Promised by
2023-06-30
Promised amount
180.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The 180 MW Ellendale facility is later shown at full capacity, and FY2024 is called its first full year of operations. No passage states when full 180 MW was first reached, so on-time status is unknown.

“built a hosting facility, and began energizing the site on March 4, 2023”
2024-05-05 · Applied Digital 424B5 filed 2024-05-06 View cached copy (2026-08-31)Live source ↗
“As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”
2024-10-09 · Earnings Release View cached copy (2026-10-08)Live source ↗Archive.org ↗
“specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”
2025-07-29 · Applied Digital 10-K filed 2025-07-30 View cached copy (2026-08-31)Live source ↗

Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Applied Digital expected the remainder of Ellendale's 180MW capacity to be turned on by the end of June 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-08)Live source ↗Archive.org ↗

Quote: “and the rest to be turned on by the end of June”

How we checked this

Checked on October 13, 2026. The cited source supports every part of this claim.

The April 6, 2023 release says the company anticipated the first half of Ellendale's 180MW would be on by end of April and the rest by the end of June.

Confirmed in the source:

What we did: Read our cached copy of IR page (ir.applieddigital.com) (https://ir.applieddigital.com/news-events/press-releases/detail/53/applied-digital-reports-fiscal-third-quarter-2023-financial/) in full (25,366 characters, retrieved October 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Earnings Release

Quote: “and the rest to be turned on by the end of June”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

confirms Applied Digital 424B5 filed 2024-05-06

Quote: “built a hosting facility, and began energizing the site on March 4, 2023”

View cached copy (2026-08-31)Live source ↗

confirms Applied Digital 10-K filed 2025-07-30

Quote: “specifically our 180 MW Data Center Hosting Facility in Ellendale, ND, which accounted for a $60.0 million increase in revenue as it was its first full year of operations”

View cached copy (2026-08-31)Live source ↗

confirms Earnings Release

Quote: “As of August 31, 2024, our 106 MW facility in Jamestown, North Dakota and our 180 MW facility in Ellendale, North Dakota are operating at full capacity.”

View cached copy (2026-10-08)Live source ↗Archive.org ↗

Record of changes

October 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Review. statement_date 2026-10-08 was the source's retrieval date; source published 2023-04-06.
October 9, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.